May 14
StevenDeamAerospace Machining, Lean Manufacturing, Precision Machining Aerospace Machining, Lean Manufacturing, Precision Machining, the seven wastes, transportation
In continuing on the topic of lean manufacturing in an aerospace machining environment today I will look at how CNC Industries handles the second waste identified in lean manufacturing. The second waste is typically identified as unnecessary transportation. At CNC Industries we look both at internal and external transportation as areas that can cause waste.
The costs of external transportation (shipping) are easy to identify. With external transportation we can easily see the cost of the transportation in dollars as we receive bills from the shipping companies. Any extra shipments obviously incur additional charges and it becomes important to keep the number of shipments required to an absolute minimum. To facilitate this we often work with our outside vendors to have our parts shipped directly from one vendor to another in the case that we have multiple outside operations back to back. As often as possible we find outside vendors that handle multiple processes to save both on the cost of production as well as the cost of transportation. In addition our AS9100 compliant procedures for selecting and purchasing from our vendors allows us confidence in the quality of the parts that we have outsourced.
Internal transportation costs are often more difficult to quantify. Many times companies will both start and stop their efforts on cycle times and overproduction as I talked about in the prior post. Transporting the parts internally more than necessary is also a form of wasted efforts. The cost of moving the parts throughout a facility may seem minor but all forms of transportation take up time and do not add anything to the value of the part. In addition every time a part is moved it is another chance for the part to become lost or damaged.
Extra transportation can occur due to a number of factors in the manufacturing process. If the parts were not scheduled correctly they may need to be moved aside to allow a different part through the machine. Poor routing of the operations that the part takes through the manufacturing process may mean that a part is scheduled through machines that are far apart in the factory. Poor engineering of the part machining process itself may mean that the part has more machining operations than necessary. Any of these items may add additional internal transportation and raise the cost and potentially lower the quality of the part.
Our ERP System – Job Manager 2 – allows us to schedule our parts with confidence that they are engineered and routed correctly. In addition to the initial engineering and routing we have a comprehensive corrective action system and Process Change Request system that allow us to continually improve our processes. Each time we manufacture a part we are able to review and adjust the process and operations as necessary to make the parts even better and more efficiently than the last time.
Aerospace machining and the high mix / low volume work that comes with it creates additional challenges in scheduling. Our engineering processes are designed to quickly work through the numerous issues with new parts and smaller batches. Our scheduling module in Job Manager 2 has a visual scheduling board that allows us to quickly determine the best routing of each part and quickly determine any problems with the processes involved. Job Manager 2 also allows us to analyze each part and quickly find any areas that have lower efficiency so that we may quickly focus our efforts in the appropriate places.
- – – -
CNC Industries is a Fort Wayne, Indiana based machine shop specializing in precision CNC machining, fabrication and assembly of application-critical and custom machined parts for the Aerospace, Defense, Medical, Industrial and Transportation markets. The company presently employs approximately 55 people.
- – – -
May 14
StevenDeamAerospace Machining, Lean Manufacturing, Precision Machining Aerospace Machining, Lean Manufacturing, Precision Machining, the seven wastes, transportation
due to a few issues on renaming the old post I am repeating the original post with the original title.
In continuing on the topic of lean manufacturing in an aerospace machining environment today I will look at how CNC Industries handles the second waste identified in lean manufacturing. The second waste is typically identified as unnecessary transportation. At CNC Industries we look both at internal and external transportation as areas that can cause waste.
The costs of external transportation (shipping) are easy to identify. With external transportation we can easily see the cost of the transportation in dollars as we receive bills from the shipping companies. Any extra shipments obviously incur additional charges and it becomes important to keep the number of shipments required to an absolute minimum. To facilitate this we often work with our outside vendors to have our parts shipped directly from one vendor to another in the case that we have multiple outside operations back to back. As often as possible we find outside vendors that handle multiple processes to save both on the cost of production as well as the cost of transportation. In addition our AS9100 compliant procedures for selecting and purchasing from our vendors allows us confidence in the quality of the parts that we have outsourced.
Internal transportation costs are often more difficult to quantify. Many times companies will both start and stop their efforts on cycle times and overproduction as I talked about in the prior post. Transporting the parts internally more than necessary is also a form of wasted efforts. The cost of moving the parts throughout a facility may seem minor but all forms of transportation take up time and do not add anything to the value of the part. In addition every time a part is moved it is another chance for the part to become lost or damaged.
Extra transportation can occur due to a number of factors in the manufacturing process. If the parts were not scheduled correctly they may need to be moved aside to allow a different part through the machine. Poor routing of the operations that the part takes through the manufacturing process may mean that a part is scheduled through machines that are far apart in the factory. Poor engineering of the part machining process itself may mean that the part has more machining operations than necessary. Any of these items may add additional internal transportation and raise the cost and potentially lower the quality of the part.
Our ERP System – Job Manager 2 – allows us to schedule our parts with confidence that they are engineered and routed correctly. In addition to the initial engineering and routing we have a comprehensive corrective action system and Process Change Request system that allow us to continually improve our processes. Each time we manufacture a part we are able to review and adjust the process and operations as necessary to make the parts even better and more efficiently than the last time.
Aerospace machining and the high mix / low volume work that comes with it creates additional challenges in scheduling. Our engineering processes are designed to quickly work through the numerous issues with new parts and smaller batches. Our scheduling module in Job Manager 2 has a visual scheduling board that allows us to quickly determine the best routing of each part and quickly determine any problems with the processes involved. Job Manager 2 also allows us to analyze each part and quickly find any areas that have lower efficiency so that we may quickly focus our efforts in the appropriate places.
- – – -
CNC Industries is a Fort Wayne, Indiana based machine shop specializing in precision CNC machining, fabrication and assembly of application-critical and custom machined parts for the Aerospace, Defense, Medical, Industrial and Transportation markets. The company presently employs approximately 55 people.
- – – -
May 07
StevenDeamUncategorized
As I talked about in the last post, I will be examining the seven wastes identified in lean manufacturing and showing how CNC Industries handles each in a high mix / low volume aerospace machining environment. The first of the seven wastes is Overproduction. Overproduction is using more resources than necessary to create and deliver a part to the customer. Overproduction can be further defined as producing more, sooner or faster than what is necessary. Elimination of overproduction is a large factor in Just-In-Time systems that many manufacturers are focusing on. Just-in-time has a goal of eliminating inventory and producing or ordering material to arrive just in time for the operation that it is needed in.
Batch size is a large factor to consider when looking at overproduction. It is important to not produce too many parts – this leads to storing the excess parts in inventory for an excessive amount of time. However, in an aerospace machining environment the complexity of the parts is prohibitive to a true just-in-time system. When a part may take 6-8 weeks to manufacture and only a small amount of the parts are needed each week to create a new batch for every shipment would necessitate setting up a new batch each week and having multiple batches open at the same time. The logistics of tracking all of these batches combined with the costs and time of setting up a machine each week for the same part would be prohibitive. In addition to the setups and the logistics, material orders would necessarily be smaller and more frequent which would eliminate cost savings in ordering and require more time in purchasing and receiving material. Of course a production facility can avoid many of these pitfalls by having specially made machines that are dedicated to a certain process or part. In a high mix environment, machines tend to be needed for many different parts and cannot be dedicated to a select group of part.
Instead for a high-mix low volume aerospace machining facility, selecting the right batch size includes factoring in the setup costs and the lead time to create a batch that is a reasonable multiple of an individual shipment. In the above example it may be seen that a batch that is the equivalent of 10 weeks of shipments is the optimum size to reduce overproduction and minimize inventory storage time as well. The key is to account for holding costs, batch setup costs, and the estimated demand on a given machined part. Our ERP system, Job Manager 2, has a module to handle these calculations and give a suggested batch size in order to lower the overproduction to the lowest feasible amount. Selecting the right batch size is of paramount importance in attempting a lean operation in an aerospace machining environment that tends to have high mix and low volume production.
CNC Industries solves the problem of overproduction waste through efficient information handling and analysis. We have strong visualizations of our production and inventory and we regularly examine our production to ensure optimum batch size. Our ERP system both handles the batch size determination and the scheduling of the new batches to ensure that parts are produced at the right time and with the right quantity. When maintaining a Kan-Ban System for our aerospace customers it is vital that we both maintain enough inventory to handle their surges in demand, as well as minimize our batch size to allow us to produce the wide variety of parts that are requested.
- – – -
CNC Industries is a Fort Wayne, Indiana based machine shop specializing in precision CNC machining, fabrication and assembly of application-critical and custom machined parts for the Aerospace, Defense, Medical, Industrial and Transportation markets. The company presently employs approximately 55 people.
- – – -
May 07
StevenDeamAerospace Machining, Lean Manufacturing, Precision Machining Aerospace Machining, Lean Manufacturing, overproduction, the seven wastes
As I talked about in the last post, I will be examining the seven wastes identified in lean manufacturing and showing how CNC Industries handles each in a high mix / low volume aerospace machining environment. The first of the seven wastes is Overproduction. Overproduction is using more resources than necessary to create and deliver a part to the customer. Overproduction can be further defined as producing more, sooner or faster than what is necessary. Elimination of overproduction is a large factor in Just-In-Time systems that many manufacturers are focusing on. Just-in-time has a goal of eliminating inventory and producing or ordering material to arrive just in time for the operation that it is needed in.
Batch size is a large factor to consider when looking at overproduction. It is important to not produce too many parts – this leads to storing the excess parts in inventory for an excessive amount of time. However, in an aerospace machining environment the complexity of the parts is prohibitive to a true just-in-time system. When a part may take 6-8 weeks to manufacture and only a small amount of the parts are needed each week to create a new batch for every shipment would necessitate setting up a new batch each week and having multiple batches open at the same time. The logistics of tracking all of these batches combined with the costs and time of setting up a machine each week for the same part would be prohibitive. In addition to the setups and the logistics, material orders would necessarily be smaller and more frequent which would eliminate cost savings in ordering and require more time in purchasing and receiving material. Of course a production facility can avoid many of these pitfalls by having specially made machines that are dedicated to a certain process or part. In a high mix environment, machines tend to be needed for many different parts and cannot be dedicated to a select group of part.
Instead for a high-mix low volume aerospace machining facility, selecting the right batch size includes factoring in the setup costs and the lead time to create a batch that is a reasonable multiple of an individual shipment. In the above example it may be seen that a batch that is the equivalent of 10 weeks of shipments is the optimum size to reduce overproduction and minimize inventory storage time as well. The key is to account for holding costs, batch setup costs, and the estimated demand on a given machined part. Our ERP system, Job Manager 2, has a module to handle these calculations and give a suggested batch size in order to lower the overproduction to the lowest feasible amount. Selecting the right batch size is of paramount importance in attempting a lean operation in an aerospace machining environment that tends to have high mix and low volume production.
CNC Industries solves the problem of overproduction waste through efficient information handling and analysis. We have strong visualizations of our production and inventory and we regularly examine our production to ensure optimum batch size. Our ERP system both handles the batch size determination and the scheduling of the new batches to ensure that parts are produced at the right time and with the right quantity. When maintaining a Kan-Ban System for our aerospace customers it is vital that we both maintain enough inventory to handle their surges in demand, as well as minimize our batch size to allow us to produce the wide variety of parts that are requested.
- – – -
CNC Industries is a Fort Wayne, Indiana based machine shop specializing in precision CNC machining, fabrication and assembly of application-critical and custom machined parts for the Aerospace, Defense, Medical, Industrial and Transportation markets. The company presently employs approximately 55 people.
- – – -
May 05
StevenDeamAerospace Machining, Lean Manufacturing, Precision Machining, Technology Aerospace Machining, Lean Manufacturing, overproduction, wastes
Lean manufacturing is a concept that most businesses strive for and many claim. The primary concept of lean manufacturing is eliminating all unnecessary costs and time associated with production. The primary way most companies will start with Lean is to manufacture parts as fast as possible – to get as much production from each machine as possible. As the cycle time decreases wasted machine time decreases as well. This is a great start to lean manufacturing, but it is also the most common method. Many companies focus on cycle time reduction almost entirely in their lean efforts.
Cycle Time reduction works best in environments where a machine shop is producing the same part for a long duration. This is typically a full production shop and will have dedicated machinery to optimize a single process to the fullest extent possible. In the aerospace machining industry or custom machined parts production we are not producing high enough volumes of many parts to dedicate an entire machine to a single part. As such aerospace machine shops and custom manufacturing shops (or job shops) will face additional difficulties in going ‘lean’.
Adjusting the cycle time down by 10% is not as effective of a lean tool when machine time may only be 60% or less of the time spent on producing a given part. The lower the proportion of machine time to non-machine time in a job, the more important it is to go lean in additional ways. in connection to that – the more often a machine needs to be set up for a new job the more non-machine cost is in the job – for reference a single aerospace machined part may have 5 or 6 separate machining operations each requiring an additional setup on the machine. Transferring the material to different areas, setting up the machine, inspecting the part throughout production, and other items add to the non-machine time at every step.
Over the next few posts I will be looking at the 7 wastes identified in a typical lean manufacturing implementation and how CNC Industries deals with each on in relation to our low volume / high mix work. We have some production jobs as well, but those are handled in slightly different ways, and will be discussed at a later time.
- – - -
CNC Industries is a Fort Wayne, Indiana based machine shop specializing in precision CNC machining, fabrication and assembly of application-critical and custom machined parts for the Aerospace, Defense, Medical, Industrial and Transportation markets. The company presently employs approximately 55 people.
- – - -